City of Irving Road to the Future Project Continues Ahead to Phase 2

Irving’s “Road to the Future: $100 Million in 5 Years” program is currently in its fifth year with city leaders planning the next phase of the ambitious, cross-departmental program.

Launched in 2017, the Road to the Future Program has been an ongoing effort to rehabilitate, reconstruct and proactively maintain 1,440 lane-miles of Irving’s streets. The project is a collaborative effort between the Capital Improvement Program, Traffic and Transportation, and Water Utilities departments to reconstruct and rehabilitate sidewalks, curbs and gutters; to replace pavement, water and wastewater mains and lines; and to repave neighborhood streets and corridors.

City leadership is looking toward the next phase of the project, which will run from 2023 to 2027. Several major construction projects throughout Irving are included in the list. The first is Esters Road, which is currently in the early design stage from State Highway 183 to Rochelle Road. Construction on Esters is expected to begin in fiscal year 2024. Additionally, the city will begin design work on three segments of Valley View Lane from Rochelle Road to just past Belt Line Road. Also included in this design work will be Rochelle Road from Valley View Lane to Andalusia Street including a new bridge over Estelle Creek.

As Phase 1 of the Road to the Future project nears its five year mark, below are projects that have been completed, are currently under construction or are under design.

COMPLETE

  • Hawthorne and Abelia Streets: $2.9M – Paving, drainage and utility improvements, as well as sidewalks. 
  • Drayton Court: $400K – Retaining wall and pavement improvements, as well as sidewalks. 
  • Las Colinas Boulevard Phase 3 (Brazos Drive to Lake Carolyn Parkway): $7.3M – Paving, drainage and utility improvements, as well as sidewalks. 
  • Glenmore and Shepherd streets: Sixth Street to Irving Boulevard.

ONGOING CONSTRUCTION

  • Hard Rock and Pioneer: $9.9M – Paving, drainage and utility improvements, as well as sidewalks. 
    • Slated for completion in September 2023.    
  • Regent Boulevard (Kinwest Parkway to Belt Line Road): $7.6M – Paving improvements, including sidewalks. 
    • Project slated for completion in February 2024. 

UNDER DESIGN

  • Delaware Street, Carroll Avenue and Delaware/Carroll Connector: $4.9M – Paving, drainage and utility improvements, as well as sidewalks.
    • Construction estimated to begin after the Municipal Drainage Utility project, Pioneer Phase 1 and 2 Storm Pipeline are complete. 
  • Lindy Lane Phase 1 (Balleywood Road to Irving Heights): $2.3M – Paving, drainage and utility improvements, as well as sidewalks.
  • Cedar Drive: $1.2M – Paving, drainage and utility improvements, as well as sidewalks. 
    • Construction estimated to begin after the Municipal Drainage Utility project, Pioneer Phase 1 and 2 Storm Pipeline are complete. 
  • Chamberlain Street (Nursery Road to Balleywood Road): $3.1M – Paving, drainage and utility improvements, as well as sidewalks. 
  • Esters Road (Twin Falls Street to Rochelle Road): $6.7M – Paving, drainage and utility improvements, as well as sidewalks.